This Steam Blowing procedure is intended to provide general application guidance and establish controls during Steam Blowing of piping and equipment. The purpose of steam blowing, prior to start-up of a new unit, is to remove any foreign material in the superheater and steam piping after the erection completion. Considerable …
Read More »Monthly Archives: September 2017
Steam Boiler Alkali Boil out Procedure
Boiler Alkali boil out is carried out to remove material such as lubricants, oil, and rust. During the manufacturing of seamless steel tubes, mill scales are bound to be formed, and some of these can remain inside. During fabrication and erection of the pressure parts, some amount of oil and …
Read More »Boiler gas tightness test procedure
We will discuss important steps involved in Boiler gas tightness test procedure. -Close all the dampers in the grate hopper of the boiler. -Run the FD fan and open all the dampers excluding the dampers in the grate hopper. Keep air pressure and running time as approved by design. Detect …
Read More »Boiler refractory dry out procedure
Boiler Refractory dry out is to ensure proper drying, curing of refractory applied on furnace and other components. The refractory usually undergoes considerable chemical changes, during initial heating. Controlled heating, through these reactions ensures maximum strength. While heating, there must be free air flow over the system to ensure removal …
Read More »Water tube Boiler Commissioning Procedure and Checklists
The operation of checking the equipment and tuning them before putting into commercial operation is commonly termed as ‘commissioning’. The boiler commissioning activity includes the following: Boiler Inspection, pre-operation checking and preparation of the equipment including specialized cleaning. Trial run, initial operation and performance monitoring. Many of the equipment including …